High-Voltage Maintenance - Network Services at Risk
Resolved
Jun 5, 2026 at 4:00am UTC
Maintenance ended
Affected services
Created
Jun 4, 2026 at 8:00pm UTC
The Campus Infrastructure department, supported by specialist electrical contractors, will be carrying out statutory high‑voltage (HV) maintenance across several University substations. This essential work is required to maintain the safety, compliance, and reliability of the University’s electrical infrastructure.
Although this work is not IT‑led, it may have an impact on IT and network services in affected buildings. Power interruptions during the maintenance windows may affect equipment that supports wired (Ethernet) and wireless (Wi‑Fi) connectivity, meaning network services may be at risk while work is underway.
Planned maintenance schedule
- Thursday 4 June 2026
- L Substation – Power shutdown
- Buildings and areas affected:
- The Edge Building
- East Building
- STV fencing hall / building
- STV tennis courts
- STV CHP plant room
- STV (main building)
- External areas
- East Car Park (including power to feeder pillar, EV chargers, and street lighting)
- Arrivals Square bus stop and reception hut (power, lighting, and heating)
- The Edge Building
- Lift outages during this period:
- East Building goods lift
- East Building passenger lift
- The Edge passenger lift
- STV (main building) passenger lifts
- East Building goods lift
We recommend users in affected buildings save their work in advance and plan accordingly. Updates will be provided via the status page if the expected impact changes.
Affected services